Bakun compensation: Dispute delaying payments
By Joseph Tawie
KUCHING: Chairman of the Bakun Resettlement Committee James Masing has admitted that some of the Bakun claimants have not been compensated.
Posted in Dam campaign on August 12, 2010 | Leave a Comment »
By Joseph Tawie
KUCHING: Chairman of the Bakun Resettlement Committee James Masing has admitted that some of the Bakun claimants have not been compensated.
Posted in Penans on August 12, 2010 | Leave a Comment »
| Longhouses of 500 Penans razed, two timber giants donate RM900 | |||
|
|||
| MIRI – Some 500 Penans lost everything when fire razed their two longhouses last week and two timber giants operating in the area came forward to give the fire victims a donation – the total amount: RM900. (more…) |
|||
Posted in Dam campaign on August 12, 2010 | Leave a Comment »
| Another dam will not benefit Sarawak people, says Kuching MP | // <
Posted in Dam campaign on August 12, 2010 | Leave a Comment »
August 11, 2010, Wednesday(Borneo Post)
BAKUN: Bakun Dam’s turbine-8 will be the first of the eight turbines to generate the dam’s first electricity.
Project developer, Sarawak Hidro Sdn Bhd managing director, Zulkifle Osman said turbine-8 located at the Bakun power house is expected to generate electrical power of 300 megawatt somewhere in July, 2011 if the impounding or flooding permit is issued by the Sarawak government by this month.